Page 1 of 1

Replace part with updated part

Posted: Wed Oct 02, 2019 1:29 pm
by David_Lelen01
Is it possible to replace a part in a job file with an updated version of the part? I created a job and sent it to the machine to be cut. The customer has requested a dimension be changed slightly, luckily before the part was actually cut. I was wondering if since i have the job already set up with the operations and lead-in locations, is it possible to replace the existing part with a updated copy of the part or is it best to start from scratch?

Re: Replace part with updated part

Posted: Wed Oct 02, 2019 1:42 pm
by Les Newell
Yup. If you have a multi-part job make sure the correct part is selected. Now File->import drawing. When the drawing options box pops up make sure you select 'current position'. As long as the dimensions are close the start points, tabs etc should be mapped to the new drawing.

Re: Replace part with updated part

Posted: Wed Oct 02, 2019 2:18 pm
by David_Lelen01
Awesome! That's perfect! Thanks Les!

Re: Replace part with updated part

Posted: Thu Oct 17, 2019 7:25 pm
by motoguy
Just a heads up, MAKE SURE that you have the proper part highlighted, or you can import a drawing of a completely wrong part. lol